PRINCE2Practitioner Training Questions have been Updated

By Examgood  |  October 27,2020 04:31 AM

PRINCE2Practitioner training questions have been updated, which are helpful in the preparation. PRINCE2 Practitioner exam is aiming to measure whether a candidate could apply PRINCE2 to the running and managing of a non-complex project within an environment supporting PRINCE2. The purpose of the Practitioner certification is to confirm whether you have sufficient understanding of how to apply and tailor the method in a range of different project environments and scenarios.

 

PRINCE2Practitioner Training Questions have been Updated

 

PRINCE2Practitioner Exam Information


Exam Duration: 150 minutes
Number of questions: 68
Passing score: 38/68 required to pass=55%
Exam format: Open book exam

PRINCE2 Practitioner Target Audience


PRINCE2 Practitioner certification is aimed at project managers, aspiring project managers and anyone who manages projects. It is also relevant to other key staff involved in the design, development and delivery of projects, including: Project Board members, Team Managers, Project Assurance, Project Support and operational line managers/staff.

Study PRINCE2Practitioner Updated Training Questions


The updated PRINCE2Practitioner training questions can help you test all the related information. Share some updated PRINCE2Practitioner exam training questions and answers below. 
1.The Manage by Exception principle sets tolerances for six areas of the project, Time. Cost and Quality are three of them, what are the other three?
A. Scope, People & Resources, Benefit
B. Scope, Risk, Product
C. Risk, Benefit, Product
D. Scope, Risk, Benefit
Answer: D

2.Which principle is supported by the activity Evaluate the Project?
A. Continued Business Justification
B. Defined roles and responsibilities
C. Learn from experience
D. Manage by stages
Answer: C

3.Which of the following activities is NOT an action of preparing for planned closure?
A. Update the project plan with actual
B. Update the Project Management Team
C. Request a product status account
D. Confirm project has delivered what is defined in Project Product Description
Answer: B

4.Which of the following statements is FALSE regarding the Continued Business Justification?
A. The justification for the project must remain the same throughout the project.
B. The justification for the project should remain vabd.
C. The justification for the project may change.
D. If the project is no longer justified it should be stopped.
Answer: B

5.Which of the following activities could trigger the production of an exception plan?
A. Review Stage status
B. Giving ad hoc direction
C. Escalating a project issue
D. Report stage end
Answer: B
Related News
53kf email[email protected] [email protected]
Montag-Samstag [9:00-18:00]   

Share on

LiveZilla Live Chat Software